City of Cypress

5275 Orange Avenue ~ Cypress, CA 90630 ~ 714-229-6700

Public Works Department
City Council Approves Plans for Sewer Improvements Project 77

On April 8, 2013, City Council approved plans and specifications for Various Sewer Improvements, Public Works Project No. 77. This sewer project will rehabilitate 2,673 linear feet of 8-12 inch vitrified clay pipe (VCP), and other incidental items of work at various locations throughout the City:

Sewer Improvements Project 77
Print pdf map

The City of Cypress views this sewer project as an important Public Works project beneficial to the community. Your cooperation during all phases of construction will be necessary for the safe and successful completion of the project. The sewer repairs are designed to extend the useful life of the sewer system. Work throughout the City is scheduled to begin September 2013, with the project tentatively scheduled for completion in February 2014.

All parking restrictions will be posted 48-hours in advance and door hangers will be distributed to all affected residences and businesses. Major arterial streets will be done in stages to allow for access at all times. For your SAFETY and the safety of your family and visitors, please stay away from equipment and construction areas. Please keep your children from harm and instruct them to stay clear of all construction activities. We appreciate your cooperation and look forward to a quick and successful project completion.

To ensure open lines of communication with businesses and residents, the City has designated a project manager and project inspector to handle all aspects of the project. To ensure quick response to your inquiries, comments, and concerns, please call:

Project Foreman:
Stelian Onufrei
MMC, Inc. (714) 240-3698

Project Inspector:
Steve Patterson
(949) 616-4669

Project Manager:
Nick Mangkalakiri
(714) 229-6729